WEEK 3 -- ALLEN ROAD LIVING SHORELINE POST CONSTRUCTION REPORT

The Shoreline continues to be battered with sustained southerly and easterly 15 to 25 knot winds, with tides running 1 to 2 feet above normal. Additional sand bags were place along the front row and tied together. The entire project is now covered with 4” to 8” of gravelly sand.



Photo taken May 17, 2011

Even though a substantial amount of sand covers the spartina, the rhizome plants still grow through the sand to reach the surface. At this point in time, it is not known how much sand cover it takes to prevent the plants from having sustained growth.

 Photo taken May 18, 2011



It is noted that in future projects biologs may not be needed because the plants, as long as they are well anchored, seem to tolerate the water turbulence. The biologs are a hindrance because they trap sand. It would be better to just use the heavy duty 900 Coir matting alone by burying and staking the leading and trailing edges. In this way the water can easily ebb and flow over the matting and plants without accumulating any sand. In order to do this, we would have to eliminate the metal staples that don’t work very well, in favor of ½” x 1” x 16” wooden stakes with ¼” holes drilled thru the top to connect the matting to the stakes driven just below beach surface and attached with plastic zip ties. The plants could then be tied with jute twine to the matting much the same way as tomato plants are tied to stakes. The savings by eliminating the biologs for the 200 feet would be about $ 4,000. That savings could be utilized for increased shoreline footage. That would also make the project less labor intensive. We could probably do 320 lineal feet for what it cost us to do 200 feet.





Submitted by
BSHCA member
William E. McGrath, PLS
Riparian Consultant







WEEK 2 -- ALLEN ROAD LIVING SHORELINE POST CONSTRUCTION REPORT

With sustained southerly and easterly 15 to 25 knot winds, the tide continues to remain 1 to 2 feet above normal. The front row of biologs continue to be battered by heavy waves that are sometimes reaching the toe of the scarping and completely inundating the entire project with at least a foot of water.
Photo taken May 11, 2011
Note the spartina growing under water


We received 300 free recycled 50 lb. feed bags from Manchester Hills Estate Farm and Winery in Ohio. Fred Bekiarian, Bill Grochowicz, Bill & Marion McGrath continued to fill sand bags and place them along the face of the front row of biologs to help save the project from complete destruction. The spartina seems to thrive under water but, it was being covered over by more and more sand from the waves being trapped between the two rows of biologs. The accumulated sand was used to fill the sand bags and replaced out front along the face of the biologs.

Submitted by
BSHCA member
William E. McGrath, PLS
Riparian Consultant

WEEK 1 -- ALLEN ROAD LIVING SHORELINE POST CONSTRUCTION REPORT

5:00 PM Sunday May 1st the living shoreline was completed with the goose netting installed around the entire perimeter. All that remained to be done was to plant about 9 more flats of spartina alterniflora that was left over.
That evening the beach was subjected to strong 20 knot winds from the south and east. The biologs held but the splashing over the top deposited about 6 inches of sand on a 6 ft. x 20 ft. section on the north end. There was additional sand deposited from the splashing on the south end but only about a third of what was deposited on the north end. Additionally, there was sand creeping in under the logs at the seams in two or three places.
Monday evening it was decided that we had to place sandbags along the first row of biologs in order to save our project.
Tuesday evening the shoreline was battered with even stronger winds and waves from the southeast. Bill Grochowicz, Fred Bekarian, Bill and Marion McGrath immediately placed 100 sandbags along and on top of the logs for about 40 ft. of the north section and about 30 ft. of the south section.

Photo taken May 5, 2011



On Wednesday we noted that a 4 ft. section of the end of a biolog gave way about 60 or 70 feet from the south end. We also noted that the front row of logs actually sank in places. In some places the logs sunk as much as 12 inches. In the area where the biolog failed we noticed that 4 to 6 inches of sand washed out from under the matting taking the previously planted spartina with it. This left the staples partially exposed. The area amounted to a 6 ft. x 12 ft. section. We immediately placed another 100 sand bags along the failed area and added more bags on the north and south end. We used the sand that splashed over the logs to fill the bags. This seemed to work quite well but, it was noted that we would need more sandbags to stop the sand from splashing in and to fortify the front row of logs for any major storm. 

Saturday morning Bill and Marion McGrath returned to bang down the staples that were exposed and planted two additional flats of spartina to fill in the empty spaces.

Submitted by
BSHCA member
William E. McGrath, PLS
Riparian Consultant

ALLEN ROAD LIVING SHORELINE POST CONSTRUCTION REPORT

ALLEN ROAD LIVING SHORELINE POST CONSTRUCTION REPORT

The BSHCA “Living Shoreline” was completed 5:30 PM Sunday May 1, 2011 as the goose netting was installed around the entire 424 lineal feet perimeter of the project.

We had 85 volunteers Saturday including Mayor Varano and various council members, BSHCA members, Girl Scout Troop 94, Potter School children and local residents.

We had 41 volunteers on Sunday including the Superintendant of Central Regional, the Central Regional baseball team and their girlfriends, BSHCA members and local residents.


Close to 400 photographs were taken by Nancy Wieme our webmaster and BSHCA Director and can be seen on our website at: http://www.berkeleyshores.org


Or more specifically for Saturday 4/30/2011 at:

Or Sunday 5/1/2011 at:

Our grant source allowed our one third share for the cost of the project to be paid by labor at $15 per hour per worker/volunteer.

The cost breakdown amounts to 85 volunteers times $15 times 4 hours (average) equals $5,100.00 for Saturday. 41 volunteers times $15 times 4 hours (average) equals $2,460.00 for Sunday. This totals $7,560.00 which more than covers our share of the cost. 

The Barnegat Bay Partnership utilizing federal grant sources, covered the cost of the materials which amounted to almost $7,000.00. Berkeley Township covered the cost for the state and federal permits. Berkeley Shores Homeowners and Civic Association besides organizing the project, covered the cost for refreshments (coffee, donuts, pizza, water, etc.) and contingency materials such as gloves, shovels, fertilizer, wire, equipment rental, etc.


Submitted by
BSHCA member
William E. McGrath, PLS
Riparian Consultant

LIVING SHORELINE VOLUNTEER WORK FORCE PLAN


SUPERVISOR, TEAM AND REGISTRATION COORDINATOR:   Vic L.

REGISTRATION & TEAM ASSIGNMENT CAPTAINS: Lucille P and Marion M.

TEAM CAPTAINS:    Howard H. (Team #1), Fred B. (Team #2), Mike T. (Team #3)

REFRESHMENTS AND CONTINGENCIES:  Bill G.

SURVEYING AND STAKE-OUT:  Bill M. and employee/helper.


TASK ASSIGNMENTS:

   TEAM #1:

# 1 - Carrying biologs and positioning at staked-out location.
# 4 -  Pounding the 2” x 2” x 48” oak stakes in on each side of the biologs at the marked locations leaving 12” of the stake exposed.
# 7 - Cutting a 3/8” V notch on the outside of the oak stakes or ¼” drill hole 1” to 2” down from      the top of biologs.
# 12 - Tying the coir matting with string every 12” at the coir along the splice.
# 16 - Placing the upland row of biologs and staking.


   TEAM #2:

# 2 -  Carrying oak stakes to location.
# 3 -  Marking biologs every 23 inches with a magic marker starting at 6 inches in from the end.
# 8 -  Cutting the 9 gauge galvanized wire with wire bolt cutters. Length to be determined in the field.  Cinching the stakes with the 9 gauge wire over the biologs.
# 13 - Measuring and poking the plant holes thru the coir matting every 12” each way.
# 14 - Inserting 1 tbl. fertilizer in each hole.


    TEAM # 3:

# 5 -   Carrying the coir matting rolls to the site and rolling out along the first row of biologs and
           tucking the edge of the roll under the biologs.
# 6 -   Snipping/cutting one strand of coir mat to allow room for 2” x 2” biolog stakes.
# 9 -   Measuring and the coir matting every 12” each way and securing with metal staples.
# 10 - Securing the coir matting with the wire staples where marked.
# 11 -  Rolling out and cutting the second coir matting with a 6” overlap.
# 15 -  Inserting the plants in the holes.
  

LIVING SHORELINE ORGANIZATION AND JOB TASKS


A.  Job Captains to supervise and assign volunteers to a group of tasks listed below.

B.  Registration Captains to sign in volunteers and assign to teams #1, #2 or #3

C. Bill McGrath to stake-out biolog placement with his employee Saturday morning.


TASKS:

  1. Carrying biologs and positioning at staked-out location  (males)
  2. Carrying oak stakes to location. (males or females)
  3.  Marking biologs every 23 inches with a magic marker starting at 6 inches in from  the end. (female)
  4.  Pounding the 2” x 2” x 48” oak stakes in on each side of the biologs at the marked locations leaving 12” of the stake exposed. (young males)
  5.  Carrying the coir matting rolls to the site and rolling out along the first row of biologs and tucking the edge of the roll under the biologs. (males or females)
  6.  Snipping/cutting one strand of coir mat to allow room for 2” x 2” biolog stakes. (females or students)
  7.  Cutting a 3/8” V notch on the outside of the oak stakes or ¼” drill hole 1” to 2” down from the top  of biologs. (male)
  8.  Cutting the 9 gauge galvanized wire with wire bolt cutters. Length to be determined in field. Cinching the stakes with the 9 gauge wire over the biologs. (male)
  9.  Measuring and the coir matting every 12” each way and securing with metal staples (female or child)
  10.  Securing the coir matting with the wire staples where marked. (male or female)
  11.   Rolling out the second coir matting with a 6” overlap. (male or female)
  12.  Tying the coir matting with string every 12” at the coir along the splice. (female or student)
  13.   Measuring and poking the plant holes thru the coir matting every 12” each way. (two person team measuring and poking holes (male, female or student)
  14.   Inserting 1 tbl. fertilizer in each hole. (male, female or child)
  15.   Inserting the plants in the holes. (male, female or child)
  16.   Placing the upland row of biologs and staking. (males)


FIGURES 1, 2 and 3

FIGURE 1

Project failure in Brick by private homeowner professionally installed by an environmental services company. Coir matting and Spartina alternilflora completely destroyed by nor’easter early April, 2011.









FIGURE 2

LIVING SHORELINE ORGANIZATION AND JOB TASKS

A.    Appoint 3 or 4 Job Captains to supervise a group of tasks listed below.
            Example: Fred, Howard…..etc.

B.    Appoint two Registration Captains to sign in volunteers and assign tasks listed below. Example: Marion, Lucille…..etc.

C.   Bill McGrath will be there at 7:30 with his equipment and a helper to stake-out the first row of biologs then proceed to stake-out the second row.

TASKS:

1.    Carrying biologs and positioning at staked-out location  (males)

2.    Carrying oak stakes to location. (males or females)

3.    Marking biologs every 23 inches with a magic marker starting at 6 inches in from the end. (female)

4.    Pounding the 2” x 2” x 48” oak stakes in on each side of the biologs at the marked locations leaving 12” of the stake exposed. (young males)

5.    Carrying the coir matting rolls to the site and rolling out along the first row of biologs and tucking the edge of the roll under the biologs. Note the oak stakes for the upland side of the biologs should not be driven until the coir matting is rolled out and tucked in.  (males or females)

6.    Cutting the 9 gauge galvanized wire every 30” with wire cutters. We need 200 30” lengths cut from 5 100’ long rolls. This wire will be used to cinch the stakes over the biologs. (female or child)

7.    Measuring and marking the coir matting every 12” with a magic marker for the wire staples. (female or child)

8.    Securing the coir matting with the wire staples where marked. (male or female)

9.    Cutting a 3/8” V notch on the outside of the oak stakes 2” down from the top for the wire cinches. (male)

10.   Cinching the stakes with the 9 gauge wire over the biologs. (male of female)

11.   Rolling out the second coir matting with a 6” overlap. (male or female)

12.   Measuring and marking the coir matting every 12” with a magic marker for the plant holes. (female or child)

13.   Cutting the plant holes thru the coir matting where marked.  (male or female)

14.   Inserting 1 tbl. of Osmocote 18-6-12 fertilizer in each hole. (male, female or child)

15.   Inserting the plants in the holes. (male, female or child)

16.   Placing the upland row of biologs and staking. (males)



FIGURE 3


LIVING SHORELINE VOLUNTEER WORK FORCE PLAN

SUPERVISOR, TEAM AND REGISTRATION COORDINATOR:   Vic L.

REGISTRATION & TEAM ASSIGNMENT CAPTAINS: Lucille P and Marion M.

TEAM CAPTAINS:    Howard H. (Team #1), Fred B. (Team #2), Mike T. (Team #3)

REFRESHMENTS AND CONTINGENCIES:  Bill G.

SURVEYING AND STAKE-OUT:  Bill M. and employee/helper.

TASK ASSIGNMENTS:


   TEAM #1:

     # 1 - Carrying biologs and positioning at staked-out location.
     # 4 -  Pounding the 2” x 2” x 48” oak stakes in on each side of the biologs at the marked
              Locations leaving 12” of the stake exposed.
     # 7 - Cutting a 3/8” V notch on the outside of the oak stakes or ¼” drill hole 1” to 2” down
              from the top of biologs.
    # 12 - Tying the coir matting with string every 12” at the coir along the splice.
    # 16 - Placing the upland row of biologs and staking.

   TEAM #2:

     # 2 -  Carrying oak stakes to location.
     # 3 -  Marking biologs every 23 inches with a magic marker starting at 6 inches in from the
              end.
     # 8 -  Cutting the 9 gauge galvanized wire with wire bolt cutters. Length to be determined in
              the field. Cinching the stakes with the 9 gauge wire over the biologs.
     # 13 - Measuring and poking the plant holes thru the coir matting every 12” each way.
     # 14 - Inserting 1 tbl. fertilizer in each hole.


    TEAM # 3:

      # 5 -   Carrying the coir matting rolls to the site and rolling out along the first row of biologs
                 and tucking the edge of the roll under the biologs.
      # 6 -   Snipping/cutting one strand of coir mat to allow room for 2” x 2” biolog stakes.
      # 9 -   Measuring and the coir matting every 12” each way and securing with metal staples.
      # 10 - Securing the coir matting with the wire staples where marked.
      # 11 -  Rolling out and cutting the second coir matting with a 6” overlap.
      # 15 -  Inserting the plants in the holes.